SUPPORT SERVICES CENTER


Project Scope
The Support Services facility project will provide space to expand and relocate Purchasing & Materials Management, Food Service Support, Maintenance & Operations and Graphic Arts.

Construction Budget
$9,504,000.00

Vanir - Rice & Gardner Team
Dean Lanuke - Project Manager
Dustin Fredrickson - Asst. Project Manager

Project Architect
PBK Architects

General Contractor
C.A. Walker Construction

Schedule Milestones

Maintenance & Operaions Building:
Current Phase: Construction
Contruction Start: May 30, 2017
Contract Completion: March 2018

Support Services Facility:
Current Phase: Construction
Construction Start: April 2018
Contract Completion: September 2018

Current Status - February 2018

Maintenance & Operations Building:

  • Construction is 75% complete.

  • Roof and wall panels are complete.

  • Parking and drives are complete.

  • Installing Electrical, Mechanical and Plumbing in the office area.

  • Painting of interior walls has begun.

  • Exterior cement board installed on office wing.






 
 